PPM Express Help Center

What do you need help with?

    Sorry, we didn't find any relevant articles for you.

    Send us your queries using the form below and we will get back to you with a solution.

    How to import Key Dates from Jira

    In this article, we will review how to import Jira items (tasks, bugs, user stories, features, improvements, etc.) to the PPM Express project as Key Dates.

      Jira connection is not available for Core plan. 


    If you have added Jira connection to PPM Express and linked PPM Express project to Jira project, it is possible to import items from Jira to PPM Express project as Key Dates. 

    Please note: Only those items that have 'Due date' field filled in can be imported as Key Dates from Jira to PPM Express.

    If Jira item was imported to PPM Express as Key Date and after this Due date was deleted from Jira item in Jira, this Key Date will be automatically deleted from PPM Express Key Dates after data synchronization. 

    Please note: Only users who have permissions to edit the PPM Express project can import Key Dates. 

    If the Jira connection is not added and the Jira project is not linked to the PPM Express project yet, then to be able to import Key Dates, it is required to have Manage Integrations and Edit Project permissions

    Importing Jira items as Key Dates

    To import items from Jira project as Key Dates to PPM Express project perform the following:

    1. Open the PPM Express project that is linked to the Jira project and where you would like to import Key Dates. 

    2. Navigate to the Key Dates section of the project and select the Import Key Date option. 

    If you have any Key Dates added to the project already, then select the Import Key Dates option from the sections header. 

    3. Select Jira in the Connection field. 

    4. Click on the Search field below. The list of items will start loading at once. However, if you need to find any specific item, you can start typing its name, type or ID to make the search faster.

    5. To select the items you would like to import just click on it and it will be added to the list of the selected items. When you are ready with the selection click Confirm to import the selected items to PPM Express as Key Dates. 

    You can delete the selected items from the list if necessary or open them in Jira.

    6. As you click the Confirm button the selected items will be added to the Key Dates section.

    The statuses, due date, and the names for the imported Key Dates are imported from Jira and cannot be changed within PPM Express. If there are any changes to these items in Jira, they will be applied to PPM Express Key Dates after data synchronization automatically. Only internal PPM Express fields can be edited for the imported Key Dates. 

    Statuses will be set according to the item due date, taking into account the current date: 

    • 'Done' will be set for the items that have 'Completed' status in Jira. 
    • 'Critical' will be set for the items that are late >10 days and not completed. 
    • 'At risk' will be set for the items that are late <=10 days and not completed. 
    • 'On Track' will be set for all other cases, for the items where the date field is greater than the current date (today).

    The items imported as key dates can be opened in Jira from PPM Express Key Dates section directly by clicking on the Jira icon next to each Key Date. 


    Deleting Jira items imported as Key Dates

    To delete Jira items imported as Key Dates to PPM Express perform the following:

    1. Open PPM Express project where Jira items were imported as Key Dates. 

    2. Select the Key Dates you need to delete from the list. 

    3. Click the Delete Key Date button. 

    4. Confirm that you would like to remove the Key Dates. The selected Key Dates will be deleted at once. 

    Please note: After data synchronization, the deleted Key Dates will not appear again in the Key Dates section automatically. If you need to add the deleted items again, it will be needed to import them following the steps described in the 'Importing Jira items as Key Dates' section of this article. 

    If PPM Express project is linked to Jira and Azure DevOps and the Key dates are imported from both systems, then in the Import Key dates window it will be possible to switch between these systems. Switching between the systems you can add the key dates for each system separately.

    Was this article helpful?

    Table of contents

      Still can't find what you're looking for?

      Contact Support
      Back To Top