PPM Express allows synchronizing additional data between PPM Express and Jira instances.
To set up mapping, perform the following:
1. Navigate to Configure Connections menu of the linked/imported Project.
2. Use the Configure connection button to open the Configure connection menu.
3. Select the External Items Mapping option.
You can exclude (include) items that are synchronized from Jira to PPM Express on this page.
The list of items on the Tasks Import page depends on the Project scheme in Jira. If Projects of the Classic type share the Project scheme, then the items will be the same on this page. Next-Gen Project type includes a custom number of items, so the list of items will be different.
Also, if the Project is Classic, then the fields for mapping will be taken from the Fields => Custom fields section of all Classic Projects in Jira.
If the Jira Project is Next-Gen, the fields for mapping will be taken per Project (will vary depending on the Project custom fields added to a specific Next-Gen Project.
To configure task import mapping, click on the gear button next to the required item.
You will see the predefined mapping and directions for the data exchange in Jira.
- PPM Express field – any OOB or custom field can be selected
- Jira field - any OOB or custom field can be selected
It is possible to edit any field, delete it or create a new PPM Express custom field from this page.
It is possible to delete any field, however, if you delete or change the 'Type' field the items for which this field is deleted will not be displayed in the counters of the Jira tasks page. Also, it will not be possible to filter these items by Type. If the 'Iterations' field is deleted or changed for any of the items, then the iterations of this item will not be displayed on the counters of the Jira tasks page.
If you need to set the Sprint start and end dates for the item instead of the item start date and due date, you can use the 'Sprit Start' and 'Sprint End' fields for mapping that are available in the Jira Fields section and map them with the 'Start Date' and 'Due Date' PPM Express fields.