Idea Prioritization

Idea Prioritization helps you rank the ideas submitted to a business challenge. Three methods are available — Scoring, MoSCoW and ICE. Use any one of them, or several and compare the results.

Delete

Note: Ideas are always ranked within one business challenge at a time. Ideas submitted to different challenges are solving different problems, so ranking them in one list would not be meaningful. The business challenge you select stays selected when you switch between methods.


Delete

Note: Changing ratings, dates or MoSCoW values needs Full Access to Idea Prioritization. With View Only access you can view and sort, but not change anything.



Idea Scoring

To score ideas, perform the following:

  1. Open Idea Prioritization → Scoring.
  2. Select a Business challenge.
  3. Optionally, filter by Stage — for example, score only active ideas.
  4. Select a Prioritization model. Only active idea models whose weights total 100% are listed; if there is only one, it is selected for you. If there are none, click Import a template or Create a model to set one up on the Models page. The model you last used for a business challenge is selected again the next time you open it in the same browser session.


Score matrix

The score matrix lists ideas in rows and the model's factors in columns. Each column header shows the factor's weight and value range.

  • Enter a whole number from 0 to 5 in each cell. Ratings save automatically, and the Strategic and Risk scores update as you type.
  • Other values aren't saved; the cell returns to its saved value.
  • After a valid rating, the cursor moves on to the next cell. Press Enter to move down a row, or use the arrow keys to move between cells.
  • Clear a cell to remove a rating. An empty cell means "not rated", not 0.
  • Ideas with no ratings are marked Not ranked. Their Strategic and Risk scores show — instead of 0.


Bubble chart

The bubble chart places every ranked idea by its Strategic Score (vertical, higher is better) and Risk Score (horizontal, lower is better). The chart is divided into four quadrants:

Quadrant

Meaning

Accelerate

High impact, lower risk — do these first

Invest

High impact, higher risk — worth doing, but manage the risk

Quick Wins

Lower impact, lower risk — cheap to do

Reject

Lower impact, higher risk — decline these

 

The bubble size shows how many ideas share the same scores; hover over a bubble to see them. The list next to the chart shows every idea by quadrant.


Timeline

The timeline shows ideas on a calendar. Drag a bar to move an idea in time, or drag its edge to change the duration. You can also select a bar and move it with the arrow keys; press Enter to save. The new Start Date and Finish Date are saved to the idea in PPM Express when you release the bar.

After each move, a message confirms the new dates. Click Undo in the message to put the old dates back.

Ideas without dates are listed under No dates. Click Set dates to give them a start and finish date. The finish date can't be earlier than the start date.


Publishing scores to PPM Express

To publish scores, perform the following:

  1. Click Update ideas….
  2. Review the confirmation. It lists every idea whose Strategic or Risk score will change, with the old and new values.
  3. Click Update N ideas.

Only ranked ideas whose scores differ from what PPM Express holds are included, and only the ideas shown by the current Stage filter. The button turns green while PPM Express doesn't hold some ranked idea's current scores.

Delete

Note: Click Start over to delete all ratings you entered for the ideas of the selected business challenge, with the selected model. Ratings for other challenges and other models are kept. Scores already published to PPM Express don't change. You are asked to confirm first, and this action cannot be undone.


Idea MoSCoW

The MoSCoW board has five columns: Uncategorized, Must Have, Should Have, Could Have and Won't Have.

  1. Select a Business challenge.
  2. Optionally, filter by Idea stage or MoSCoW column. Clear filters appears when a filter is on.
  3. Drag an idea into a column to set its MoSCoW value. Drag it back to Uncategorized to clear the value. You can also move cards with the keyboard: each arrow key press moves a card one column.

Each move is saved to the idea in PPM Express immediately — there is no separate save. To reverse a move, click Undo in the message that appears.

To review or reverse earlier moves, click Changes this session. Undo moves one at a time, or click Undo all to put every idea back where it was when you started. The list is kept when you switch to another method, but reloading the page clears it.


Idea ICE

ICE scores each idea on Impact × Confidence × Ease. It is a quick ranking for when a full weighted model is more than the question needs.

  • Table — choose a value for Impact, Confidence and Ease. On the 1–100 scale, type the value instead. The ICE score and rank appear once all three are scored. Choose — to clear a value.
  • Bubble chart and Histogram — see clusters and the spread of scores.
  • Filters — business challenge, idea stage, minimum and maximum ICE, and minimum Impact, Confidence and Ease.


ICE settings

Open Settings to change how ICE works:

  • Scoring scale — 1–5, 1–10 or 1–100. If you choose a smaller scale, you are warned which scores will be out of range.
  • Normalize scores — show the ICE score as Normalized (0–100) or as the Raw product.
  • Display name and Help text — rename each dimension to match your organization's terms.

Click Save settings to apply. ICE settings are shared between ideas and projects, so changing them needs Full Access to both Idea Prioritization and Project Prioritization. With less, the settings panel is read-only and says why.

To clear all ICE scores, use Start over in the settings panel. This also empties the ICE Score field in PPM Express.

Delete

Note: Each ICE score is saved to the idea's ICE Score field in PPM Express as soon as it changes. Impact, Confidence and Ease are stored in Strategy and Scenario Planner only. Saving the ICE settings updates every ICE score in PPM Express whose value changes, and clearing a rating empties the field.