Each scenario is worked through six phases. Open a scenario from the analysis to see the numbered phase steps at the top: Scoring, Modeling, Optimization, Budget Leveling, Resource Capacity and Write.
Phases 1 to 5 change nothing in PPM Express. Phase 6: Write is the one place where a scenario's selection, dates, budgets, resource plans and scores are written to PPM Express.
You can open any phase at any time, but each phase builds on the one before it. Scoring shows a check mark once every project is scored. A warning sign means the phase can't do anything yet. Point at the step to see why, for example, Needs scores from Phase 1 or Select projects in Phase 2.
If the scenario is the analysis's decision, the phase bar shows a Decision badge. Click Analysis to return to the scenario list. Use Comments, at the end of the phase bar, to leave notes about the scenario or its projects. Comments belong to the scenario, not to a single phase.

Phase 1: Scoring
Score the analysis's projects against its model. The score matrix works the same way as in Idea Scoring: enter a whole number from 0 to 5 per factor, scores are saved automatically, and the Strategic and Risk scores recalculate as you type.
Switch between the Matrix, Timeline, Bubble chart and Dependencies views. In the Matrix, use Sort by to order projects by when they were added, by Strategic score or by Risk score.

Because scores belong to the analysis, you score each project only once, and every scenario of the analysis uses the result.
- Use Add projects to add projects to the analysis.
- Remove project takes the project out of every scenario of the analysis and deletes its ratings. Its comments are kept, out of sight, and come back if you add it again. The project stays in PPM Express.
- Start over deletes all ratings in the analysis, for every scenario, and puts this scenario's projects back to Not selected.
To publish the scores to PPM Express, use Phase 6: Write.
Phase 2: Modeling
Phase 2 is where you decide which projects are in the scenario. For every project you see its Strategic and Risk scores from Phase 1, its Alignment Score, stage, budget (split into CAPEX and OPEX), benefits, ROI and dates from PPM Express.
Each project has one of these states:
State |
Meaning |
Selected |
In the scenario |
Not selected |
In the pool, but not in this scenario |
Forced in |
Always kept, whatever the score — use it for commitments that are not up for debate. Shown under Selected with a pin. |
Forced out |
Always excluded. The optimizer never picks it. |
Drag a project between the Selected, Not selected and Forced out sections, or use the actions on its card. Use the comment icon on a project's row to add a note on that project, such as why it is in or out.
The totals show how many projects are selected, their total Strategic and Risk scores, and two cards:
- Budget — the selected spend against the analysis's budget target: how much is left or how far over you are, split into CAPEX and OPEX.
- Benefits — the selected benefits, net value and ROI.
Projects whose financial data could not be read show no live data instead of being counted as zero. Click it to read that project again from PPM Express. This only reads data and changes nothing.
Optimize
Click Optimize to pick the projects with the highest total Strategic score that fit the budget target. Forced in and Forced out projects stay as they are. The totals show what changed, and Undo puts the previous selection back.
Views
Switch between Board, Timeline, Bubble chart and Dependencies.
- The dependency graph shows which projects depend on others, so you do not select a project whose prerequisite was left out. If a project depends on one outside the analysis, you can add that project to the pool straight from the graph.
- The bubble chart can show All, Selected or Not selected projects. Each project shows its state as a badge.
- Use Budget shown to show the total budget, or only CAPEX or only OPEX, on the timeline, the bubble sizes and the dependency cards.
Save as new scenario copies the current scenario, including its project selection, into a new Draft scenario. The original is unchanged.

Phase 3: Optimization
Phase 3 generates Pareto-optimal portfolios — options where you cannot improve one measure without giving up another. Instead of arguing over one answer, the team sees the real trade-offs and chooses between them.
Use the following controls:
- What-if budget target — starts at the analysis's budget target. Type another amount to see portfolios under a different budget, or clear the field for no target.
- How much risk to accept — Low: favour safer projects, Medium or High: favour higher value. Changing it resets the weights.
- Adjust weights — fine-tune the six dimensions the Balanced portfolio values: Strategic value, Benefits, Risk avoidance, Budget use, ROI and Alignment score. Weights that don't add up to 100 are scaled to 100%.
- Show portfolios — All three, or only Value Maximizer, Balanced Portfolio or Risk-Minimized.

Each portfolio card shows its totals, averages and budget used. Click Show project decisions to see which projects are in and out, and why.

Below the cards, the Best score for each budget chart plots every best-value portfolio by budget and strategic value, Value vs risk shows the trade-off between value and risk, and the Project selection matrix shows which projects each recommended portfolio includes.
Using a portfolio
- Click Select these N in Phase 2 on its card.
- Review the preview: the projects added and removed, and the Phase 2 totals before and after.
- Click Select in Phase 2.
Phase 4: Budget Leveling
Phase 4 shows each funded project's forecast budget by month or quarter, and the scenario's total spending over time. You can move projects earlier or later to even out spending. The moves are saved in the scenario as you make them. Nothing changes in PPM Express until you write them in Phase 6: Write.
Only projects the scenario funds are shown. Projects with no forecast budget are hidden unless you click Show N without a forecast.
Use the controls to explore the data:
- Monthly or Quarterly periods, and chart values Per period or Cumulative.
- Level by — CAPEX + OPEX, CAPEX or OPEX. With one type chosen, the peak, the months over the limit, the chart and the totals count only that type, but a move still moves the whole project.
- Today and Peak jump the grid to the current month or the busiest one. Past months are grey and shown as history.

Moving a project
- Drag its bar left or right, or select the bar and use the arrow keys (one week per press, or one day with Shift).
- The amounts, totals and chart update as you drag. A moved bar turns green and shows the number of days moved. A hatched outline shows where the project is in PPM Express.
- To undo one move, click × on the bar, double-click it or press Home.
The Spend limit per month is the line on the chart. Until you type a value, it is the scenario's monthly average. A value you type is saved for this scenario; click Use average to go back. The scoreboard shows the peak month and how many months are over the limit, before and after your moves.
Moves are shared with Phase 5: Resource Capacity. Reset budget changes… puts the budgets back as PPM Express has them, after a confirmation; moves on resource plans in Phase 5: Resource Capacity stay. It changes nothing in PPM Express.
Deselecting a project
To take a project out of the scenario without going back to Phase 2, click … on its row and select Deselect project.
Projects the scenario doesn't fund are listed below the grid under Deselected projects (N). They are excluded from the scenario's budget and resource demand, and their saved moves are kept.
When you're ready, click Review N moves in Phase 6 to check the moves and write them to PPM Express.

Phase 5: Resource Capacity
Phase 5 checks whether your people can deliver the scenario. It compares the planned hours of the funded projects with your resources' free capacity in each period.
- Capacity is calculated from each resource's work week, max units and non-project work for that period.
- Free capacity is capacity minus the work already planned on projects outside this scenario.
- A generic resource is treated as a pool: Backend Developer at 1200% counts as twelve people.
Reading the grid
- Group by — Role & resource, Project & role or Project & resource. With Role & resource, choose Roles + resources, Roles only or Resources only.
- View — Grid (the default), Line or Bar. Period — Month, Quarter or Year.
- Show — % (all planned work, in this scenario and elsewhere, as a share of capacity) or Hours (this scenario's planned hours). The colour gets darker as the period fills up, and a red cell is over capacity.
- Point at a cell to see the planned work, other work, capacity and what is left free. Turn on Show changes to see how much each cell changed with your moves.
- Allocations — Committed + proposed (the default), Committed only or Proposed only.
- The Max units column shows each resource's max units from PPM Express and the total for each role.
- When you expand a role or resource, an Other work line shows the hours planned on projects outside this scenario.

The resource card has four tabs: Utilization (the grid), Impact of the moves (only the people and periods your changes affected, before and after), Changes (every moved project and every piece of added capacity) and Dependency issues (projects that start before a project they depend on finishes).
Resolving an over-allocation
The Projects schedule under the grid shows one line per funded project, on the same period columns as the grid.
- Drag a project left or right to any day to see how it affects capacity. Near the 1st of a month or a whole-month move, it snaps there. You can also select a bar and use the left and right arrow keys; press Home to move it back. The move is shown and saved in days, and the project keeps its length, so a project that finishes on the last day of a month may finish on a different day after the move.
- Point at a project to see where its work lands in the grid. Click it to keep it in focus, and click Clear focus to let it go.
- Click Focus on a resource's row to show only the projects that use that resource, with its hours on each bar.
- With Move dependent projects along on (the default), moving a project later also moves the projects that depend on it, shown as Moved along. Turn it off to move one project alone.
As in Phase 4, projects that have started, finished or have actuals can't be moved.
The scoreboard at the top shows, before and after your changes: over-allocated resource-months, role-months over capacity, peak utilization, how many changes you made and how many dependency issues there are.
Adding capacity
To add capacity to an over-capacity role:
- On the role row, click + Add capacity.
- Choose the Kind (New hire, Contractor or Transfer) and the Max units (100% is one full-time person).
- Choose From and To months, starting this month or later, and click Add.
The entry appears as a green row under the role, and the role's capacity rises. Added capacity is saved on the scenario, so everyone sees it.
Reset resource changes… puts resource plans back as PPM Express has them and removes all added capacity. Moves on budgets in Phase 4 stay, and Phase 6 still writes them; to remove them, use Reset budget changes in Phase 4. You are asked to confirm.

Phase 6: Write
Phase 6 shows everything the scenario would change in PPM Express. Nothing is written until you confirm here.
The tab has four choices, all ticked to start with:
- Apply scenario selection — marks the scenario's selected projects Selected, writes the scenario name on them, records a baseline, and makes this scenario the analysis's decision. Projects the scenario doesn't select keep what PPM Express holds. A Draft scenario also becomes Active.
- Apply changes to project dates and budget data — moves each project's start and finish dates, its budget dates and its forecast budget. The baseline and actuals stay as they are.
- Apply changes to project dates and resource plan data — moves each project's start and finish dates, and its planned hours with them. Actual hours stay as they are, and capacity added in Phase 5 stays in the scenario.
- Apply strategic and risk scores — writes each scored project's Strategic and Risk score from Phase 1 to the project's Strategic Factors Score and Risk Factors Score fields. Only projects whose scores differ from PPM Express are listed, with the values now and after. A project with no ratings is skipped, so it is never written as 0.
After a write, a moved project's start and finish span the first and last day that hold forecast money or planned hours.
To write a scenario to PPM Express, perform the following:
- Open Phase 6: Write.
- Review the summary and each section. Untick anything you aren't ready to write.
- Click Write to PPM Express.
Each project shows its status as the write runs. If a project isn't written, Phase 6 says why; click Write again to retry.
After writing, the phase bar shows a Written date, and a Decision badge if the selection was written too. If there is nothing left to write, Phase 6 says PPM Express is up to date.
When PPM Express changes
When you open a selected scenario, Strategy and Scenario Planner compares the dates, forecast and planned hours it wrote with PPM Express. If they differ, it lists the changes and offers two choices:
- Load data from PPM Express — use the current PPM Express data in the scenario.
- Do not load, use stored information — keep the scenario as it is. The scenario says so at the top, each changed project is marked, and Phase 6 warns that writing overwrites the change.