This article describes the data synchronized to the PPM Express Project from an imported/linked Planner Premium Project.
In case the PPM Express Project is connected to a Planner Premium Project, the following PPM Express Project sections will be populated with data synchronized from Planner Premium, and the following information will appear in the PPM Express Project:
Summary and Timeline
In the Summary and Timeline sections, the timeline and % Complete display data synchronized from Planner Premium, showing the Project progress.
Team
The Team section displays a list of all resources with assignments on Planner Premium Project with a number of tasks assigned to each resource grouped by the task progress and status.
- In Progress Tasks – 1 – 99% value in the field ‘Progress’
- Completed Tasks – 100% value in the field ‘Progress’
- Not Started Tasks – 0% value in the field ‘Progress’
- This Week Tasks – Tasks that are executed this week
- Late Tasks - Tasks with a finish date less than Today and progress set to 0 – 99% value in the field ‘Progress’
Tasks (Schedule)
This section includes four cards where you can quickly review the task statuses, progress, and summary. All the task numbers are clickable and will open the Planner Premium task page in PPM Express, filtering out the tasks by the selected value.
You can review tasks synchronized from Planner Premium on a separate tasks page.
Key Dates
Tasks with zero (0) days Duration will be synchronized to the Key Dates section as Milestones.
Details
The fields in the Details section will be populated with values synchronized from Planner Premium according to the Project Field Mapping.