Data synchronized form Project Online Connection
This article describes what data is synchronized to the PPM Express project from an imported/linked Project Online project.
In case when PPM Express project is connected to Project Online project, the following PPM Express project sections will be populated with data synchronized from Project Online.
Summary
In the Summary section, the timeline and % Complete display data synchronized from Project Online, showing the project progress.
Key Dates
This section displays releases, key dates, and milestones created in PPM Express. In addition, PPM Express synchronizes project milestones existing in Project Online, i.e. tasks which duration equals 0 days or with start date which equals the finish date.
Timeline and table views are available for Key dates. By default timeline view is displayed, but you can switch to the table view any time if needed.
In case the milestone is synchronized from Project Online, the following information is imported to PPM Express:
Title – Milestone title
Date – Milestone finish date
Complete – %Complete:
- No – %Complete does not equal 100%
- Yes – %Complete equals 100%
Statuses:
- On Track – Finish Date is greater or equals Today;
- At Risk – The key date is late for less than 10 days (from Today);
- Critical – The key date is late for more than 10 days (from Today).
- Done - the Key date is Completed.
To create a new key date use the New key date button. On the key date creation panel select the key date type – a milestone, release or key date. Enable Show on Timeline checkbox to display the created milestone on the main progress bar in the Summary section of the project page.
Please note: Data synchronized from Project Online cannot be edited for imported milestones, i.e. Title, Date, Complete and Status fields.
To make some changes to milestone fields synchronized from Project Online, edit the milestone in the Project Online, publish the project and sync linked project in PPM Express.
The following fields can be edited in PPM Express for milestones synchronized from Project Online:
- Show on Timeline
- Description
- All custom fields created in PPM Express for Key Dates section
Team
Team section displays all resources added to the Build Team in Project Online instance. Next to each resource is displayed a total amount of assigned tasks grouped by the Status.
Task Statuses:
- In Progress Tasks – Tasks with % Complete is within 1-99%
- Completed Tasks – Tasks with % Complete = 100%
- Not Started Tasks – Tasks with % Complete = 0%
- Late Tasks – Tasks with finish date less than Today and % Complete less than 100%
- This Week Tasks – Tasks that are executed this week
Please note: In the Team section all tasks with all types are calculated: milestones, summary tasks, project summary task, child tasks.
Schedule
Schedule section displays only summary tasks, including project summary task, preserving schedule hierarchy in Project Online. From the Schedule section, you can open the Project Online tasks page and review the details for tasks synchronized from Project Online.
The following data is synchronized and displayed:
Summary Task – displays the summary task name. The summary task also contains WBS of the task For example, Summary Task – 1.1. Scope, where 1.1 – is the task WBS Scope – is the Task name
Duration – displays summary task duration in hours
Start – Summary task start date.
Finish – Summary task finish date
% Complete – display % Complete of the Summary task
Progress – is based on the number of child tasks that belong to the corresponding summary task. For example, 47/69, where 47 – number of completed tasks 69 – total number of child tasks.
Please note: Milestones are excluded from Progress calculation on the Schedule section.
Please note: Tasks status is recalculated when the project data is synchronized.
Risks
This section displays risks from the project site of the linked project.
Data from Project Online is synchronized to the PPM Express project according to the following column mapping:
Title – Risk Name
Owner – Owner
Assigned To – Assigned To
Status – Status
Category – Category
Due Date – Due Date
Probability – Probability
Impact – Impact
Cost – Cost
Description – Description
Please note: Risks synchronized from Project Online cannot be modified within PPM Express. To edit the risk, make required changes in your Project Online instance and run sync in PPM Express.
Issues
Similar to the risks section, in this section can be found Issues from the project site of the linked project.
The following column mapping is applied:
Title - Issue Name
Owner - Owner
Assigned To - Assigned To
Status - Status
Category - Category
Due Date - Due Date
Priority - Priority
Please note: Issues synchronized from Project Online cannot be modified within PPM Express. To edit the risk, make required changes in your Project Online instance and run sync in PPM Express.