How to import/link PPM Express Project to Planner Premium Project

In this article, we will review how to link the PPM Express Project to the Planner Premium Project. Also, we will review how to import Resources from Planner Premium to PPM Express. 

Delete

Note: All information in this article also applies to both Planner Premium and Project for the web environments. 


In this scenario, we consider that you are linking projects from Planner Premium to PPM Express for the first time.


Linking PPM Express project to Planner Premium 

To link the PPM Express project to the Planner Premium project, perform the following:

1. Open the PPM Express project that you would like to link to the Planner Premium project and press the Connect button.

2. On the 'Link to Project' tab, select the Planner Premium option.

3. Open the Connection drop-down and select the 'Add new connection' option.

4. As you select the 'Add new connection' option, the 'Create connection' window will be opened. Please refer to the 'How to add Planner Premium connection to PPM Express' article to add a connection.

5. When the connection is added, in the 'Select project' section, select the project from Planner Premium that you would like to link to PPM Express.

7. Click the 'Link project' button.

When linking the PPM Express Project to the Project from Planner Premium for the first time, and there are tasks within the PPM Express Project, PPM Express will suggest switching from the primary PPM Express Schedule to the Schedule synced from Planner Premium. If there are no PPM Express tasks on the Project selected for linking, the Primary Schedule will automatically switch to Planner Premium (without showing a message). 

The primary schedule setting defines from what schedule the rolled-up values will be displayed in the global Project rolled-up fields on the Project dashboard Details section. For more details, please refer to the Project Settings article. Please refer to the 'Project Schedule rolled-up fields for each connection' article for a detailed description of the roll-up fields for external connections.

Project linking will start immediately. 


Importing Projects from Planner Premium

1. On the Projects, open the Actions drop-down and choose the Import Projects option. 

2. On the Import Projects to PPM Express page, choose the source system, Planner Premium.

3. If you have the connection added, click on the connection name. If you do not have it added, click the Add new connection button. As the connection is added, you can import Planner Premium Projects to PPM Express.

4. In the next step, choose the Projects from Planner Premium you want to import into PPM Express by marking the corresponding checkboxes in the list.

Delete

Note: By default, PPM Express imports Projects using their original names, but you may change the name of any Project you import by clicking on its name in the Name in the PPM Express column. This new name will be displayed in PPM Express. 


5. When the Projects are selected, click the Import button.

When importing projects from Planner Premium, new Projects are created with the Planner Premium Primary Schedule by default. If a Project already exists, the primary schedule is also changed to the Planner Premium Schedule. 

Depending on the amount of data to process, this operation may need some time. You can see the import progress on the progress tab above the selected Projects. 

6. As soon as the Project import is completed, you will see the Already linked status for the linked Projects. 

To exit the Import Projects screen, just click on the left part of the page outside the Import Project screen. First, you will get to the step where you can add another Connection. After the first import operation, you can select another account to import your Projects from Planner Premium.

Now open one of the Projects we have just imported and navigate to the Schedule section either by clicking on the Schedule in the page navigation menu or by scrolling down the page.

This section includes four cards where you can quickly review the task statuses, progress, and summary. All the task numbers are clickable and open the Planner Premium tasks page in PPM Express, filtering out the tasks by the selected value.

You can review tasks synchronized from Planner Premium on a separate Planner Premium tasks page.

To manage your Project, use the control panel in the upper right part of the Project dashboard:

  • Force sync project. This button allows manually synchronizing your Project with the linked item at the source system. If it's grayed out, sync is currently in progress.
  • Planner Premium button opens the Planner Premium Project in a new tab. 
  • Link Project. Opens Configure connections menu for the current Project allowing changing the linked item at the source system or unlinking the Project completely.


Importing Resources from Planner Premium

In a very similar way, you can import your Resources from Planner Premium to PPM Express. 

Delete

Note: Some of the resources in the list may have the Already linked status. These resources were assigned to the Projects you have already imported and thus added to PPM Express automatically.


1. On the Resources page, open the Actions drop-down and choose the Import Resources option.  

2. On the Import Resources to PPM Express page, choose the source system, Planner Premium.

3. If the connection is added, click on its name. If the connection is not added, select the Add New Connection option. 

4. On the next step, select the Resources with Not linked status for import by checking their checkboxes.

Click the Import Resources button. 

As the import process is completed, you will see the linked status next to the Resources selected for import. 

To exit the Import Resources screen, just double-click on the left part of the page outside the Import Resources screen.